Fake data

Stock & order advice

What is on the shelf, what is on the way, and what to order now.

Last count 10 Sep 2026 by Joey · 1 material9 materials never counted, those fall back to the opening stock of 1 Aug 2026.
Order now
0
Order before next review
2
Deliveries overdue
1
On order
3
Devices shipped since count
0

Stock & order advice

Order when the position (on hand plus on order) drops to the reorder point. Most urgent first.

Enter a new count →
MaterialOn handOn orderDays of coverReorder atStatusOrder advice
Solar panelB 21–28 d · 0.1/day2 pcscount 2 8 pcsdue 1 Oct 202613 d67 d incl. on order
6LOW
EpoxyB 7–9 d · 0.9/day41 kgcount 18 +47 −2448 dempty 27 Oct 2026
16LOW
 
MastB 14–19 d · 0.1/day11 pcscount 16 −573 dempty 22 Nov 2026
5OK
 
PackagingC 10–14 d · 1.9/day165 pcscount 220 −5585 dempty 3 Dec 2026
34OK
 
AnemometerA 21–28 d · 0.1/day13 pcscount 18 −525 pcs13 d late87 d253 d incl. on order
7OK
Enclosure (WS)B 14–19 d · 0.1/day14 pcscount 19 −593 dempty 12 Dec 2026
5OK
 
Rain gaugeB 21–28 d · 0.1/day15 pcscount 20 −5100 dempty 19 Dec 2026
6OK
 
WS mainboardA 30–40 d · 0.1/day17 pcscount 22 −5113 dempty 1 Jan 2027
8OK
 
Battery (WS)B 40–54 d · 0.1/day19 pcscount 24 −5127 dempty 14 Jan 2027
8OK
 
RWS tubeB 28–38 d · 5/day650 pcscount 390 +400 −140130 dempty 18 Jan 2027
190OK
 
Flat cableC 14–19 d · 1.8/day250 pcscount 300 −50139 dempty 26 Jan 2027
39OK
 
PCB bottomA 35–47 d · 1.8/day295 pcscount 145 +200 −50300 pcsdue 2 Oct 2026164 d331 d incl. on order
90OK
PCB topA 35–47 d · 1.8/day300 pcscount 150 +200 −50167 dempty 23 Feb 2027
90OK
 
Screw setC 7–9 d · 1.9/day445 setcount 500 −55228 dempty 26 Apr 2027
28OK
 
Battery (sensor)B 40–54 d · 1.8/day570 pcscount 320 +300 −50317 dempty 23 Jul 2027
90OK
 

Shipped since the last count

Deals dated after 10 Sep 2026. This is what should have been consumed from stock.

Assumptions →
No shipments since the last count.